Upcoming Contracts

The following contracts will be available for bid during the course of the project. Requests for Proposal will be available upon public release. For additional information or to be listed in our contractor database to receive contract information, please visit the contact page.
 

Chinatown Station

Advertise date: February 27, 2012
Estimated cost: $235,000,000
Scheduled Notice to Proceed: 3rd Quarter 2012
Duration: 52 months
Length: 200 ft.
Depth: 115 ft.
Extended Cavern: 340 ft.

Includes: Station finishes, AC and DC traction power substations, elevators, escalators, lighting, emergency ventilation fans, HVAC fire alarm/ suppression/ protection, slurry or secant pile and SEM excavation, settlement monitoring, building protection, PA, CCTV, signage, installation of fare collection equipment, station start-up and commissioning.

Parties interested in this contract should e-mail Bernie Ancheta (bernie.ancheta@SFMTA.com) or call (415) 701-4278.  Please visit SFGOV.org to access the advertised bid document.  For more information on the station, please see our Chinatown Station Fact Sheet and the Chinatown Station Pre-Bid Conference Presentation.

Union Square/Market Street Station

Union Square/Market Street Station renderingAdvertise date: April 16, 2012
Estimated cost: $210,000,000
Scheduled Notice to Proceed: 4th Quarter 2012
Duration: 56 months
Length: 210 ft.
Depth: 100 ft.

Includes: Settlement monitoring, building protection, secant and inclined tangent piles, but not limited to, top-down construction, connecting to and modifying  the BART Powell Street station, station finishes, AC substations elevators, escalators, lighting, emergency ventilation fans, HVAC fire alarm/ suppression/ protection, PA, CCTV, signage, installation of fare collection equipment, and station start-up and commissioning.

Parties interested in this contract should e-mail Bernie Ancheta (bernie.ancheta@SFMTA.com) or call (415) 701-4278.  Please visit SFGOV.org to access the advertised bid document. For more information on the station, please see our Union Square/Market Street Station Fact Sheet and the Union Square/Market Street Station Pre-Bid Conference Presentation.

Yerba Buena/Moscone Station

Yerba Buena/Moscone Station renderingAdvertise date: June 2012
Estimated cost: $117,274,852
Scheduled Notice to Proceed: 4th Quarter 2012
Duration: 49 months
Length: 200 ft
Depth: 50 ft.

Includes: Station finishes, AC and DC Traction Power substations elevators, escalators, lighting, emergency ventilation fans, HVAC fire alarm/ suppression/ protection, slurry wall top-down construction, settlement monitoring, building protection, PA, CCTV, signage, installation of fare collection equipment and station start-up and commissioning.

Trackwork, Systems, and 4th and Brannan Surface Station

4th and Brannan Station renderingAdvertise date: July 2012
Estimated cost: $125,228,453
Scheduled Notice to Proceed: 1st Quarter 2013
Duration: 60 months

Includes: Testing, safety and security project certification and enabling the SFMTA to satisfactorily operate and maintain the project, including but not limited to construction of tunnel invert concrete, track emergency walkways, lighting, wet standpipes, undercar deluge, radio repeator stations and antennae, overhead contact system, traction power feeders and detection system, switch machines, CCTV, SCADA, communications sytem, ticket vending machines, advanced train control system, train destination audible and visual annoucement displays and other passenger information systems, systems monitoring/control centers and signage.

 